KMC, Sepa put on notice on plea against Nehr-e-Khayyam’s conversion into recreational spot

November 05, 2026
View of the ongoing concrete construction on Nehr-e-Khayyam in Clifton on October 15, 2026. —Facebook@saveKHIparks
View of the ongoing concrete construction on Nehr-e-Khayyam in Clifton on October 15, 2026. —Facebook@saveKHIparks

The Sindh High Court (SHC) has issued notices to the Karachi Metropolitan Corporation (KMC), Sindh Environmental Protection Agency (Sepa) and others on a petition that challenged the conversion of the Nehr-e-Khayyam from its lawful status and primary function as a storm-water drain into a recreational park and commercial venture.

The petitioners , KMC’s City Council Leader of the Opposition Saifuddin Advocate and others, had submitted that they and other residents of Clifton were aggrieved by the ongoing construction and development activities being carried out in and around the Nehr-e-Khayyam.

They said ongoing construction raised serious concerns regarding the preservation of the natural waterway, potential adverse impact upon the city’s rainwater drainage system and possible commercial utilisation of the land of the waterway.

They submitted that they had serious reservations regarding the transparency, planning and environmental implications of the impugned project, particularly in the absence of publicly disclosed information concerning the approved PC-I, environmental impact assessment (EIA), technical feasibility, drainage capacity, sewage-disposal arrangements and proposed utilisation of the land.

They said that construction, alteration and development were being carried on quickly on the said waterway and the mega project was being preceded without a proper technical and environmental assessment, which was not in accordance with applicable laws, environmental safeguards and approved urban planning standards.

They said that narrowing, obstructing or altering the natural waterway without technical and environmental assessments may adversely affect the flow and disposal of rainwater, particularly during the monsoon season, endangering public safety and the civic interests of the residents of Karachi.

The petitioners also opposed any unauthorised commercial activity or encroachment upon the waterway/public land and emphasised the need for a separate and adequate sewage-disposal system to prevent further degradation of the waterway and the surrounding environment.

The SHC was informed that it recently came to the knowledge of the petitioners that the local government secretary had entered into an agreement with a private organisation for the construction of a drain at Nehr-e-Khayyam, initially approved at an estimated cost of Rs499.993 million, whereas the subject waterway, extending approximately 2.5 kilometres, was originally reserved for the conveyance of stormwater.

They said that the project, as presently conceived and being implemented, had materially departed from its original purpose and its present feasibility and adequacy were seriously questionable in the event of heavy rainfall.

The petitioners said the impugned actions, omissions and permissions of the respondents, insofar as they authorised or facilitated the conversion, narrowing, obstruction or change of the use of Nehr-e-Khayyam from its designated function as a canal or storm-water drain were contrary to the approved master plan and the applicable planning and building regulations.

They said the impugned actions, if allowed to continue without lawful authority, adequate technical assessment and compliance with the applicable environmental safeguards, exposed the residents of Karachi, particularly those residing in and around Clifton, to avoidable risks of flooding, waterlogging and environmental degradation.

Their counsel Sajjad Ahmed said that Sepa rules had not been complied with and construction over the subject canal was illegal and unlawful.

The high court was requested to declare that the Nehr-e-Khayyam shall be preserved and maintained for its lawful purpose and primary function as a storm-water drainage channel, and that no change of its status, character, course, width or use shall be permitted in a manner inconsistent with its drainage function.

A division bench of the high court headed by Justice Riazat Ali Sahar after a preliminary hearing of the petition issued notices to the KMC, Sepa and others, and called their comments on November 19. The high court also directed the office to tag the petition with an identical matter, which is already pending before the court.