Hydropower is a critical pillar of Pakistan’s economy, energy security and water management. It provides low-cost, low-carbon electricity while supporting agriculture through the country’s irrigation system. According to Nepra’s State of the Industry Report 2025, hydropower accounted for 11,500MW, or about 28 per cent, of Pakistan’s total installed electricity generation capacity during the fiscal year 2024-25 and generated 39,973 GWh.

POWER PROJECTS

Small hydro and big impact

Hydropower is a critical pillar of Pakistan’s economy, energy security and water management. It provides low-cost, low-carbon electricity while supporting agriculture through the country’s irrigation system. According to Nepra’s State of the Industry Report 2025, hydropower accounted for 11,500MW, or about 28 per cent, of Pakistan’s total installed electricity generation capacity during the fiscal year 2024-25 and generated 39,973 GWh.

With growing demand for renewable energy and continued exposure to imported fossil fuels, Pakistan needs to make better use of its substantial hydropower potential. Wapda has expanded its hydropower base while pursuing several major projects. It operates 21 hydropower stations with a combined installed capacity of approximately 9,368MW, accounting for more than 80 per cent of the country’s installed hydropower capacity. Alongside new projects, Wapda is rehabilitating, refurbishing and modernising ageing power stations to recover lost capacity, improve efficiency and reliability, and extend their useful operating lives.

Major initiatives include the Mangla Hydropower Refurbishment Project, with an installed capacity of 1,310MW, and the Second Rehabilitation Project of Warsak Hydel Power Station, with a capacity of 243MW. Both form part of Wapda’s wider programme to improve existing assets and their availability. The rehabilitation of smaller stations is equally important, although it receives less public attention.

On December 11, 2025, the media reported that the French Development Agency (AFD) was providing 351.50 million euros in loans for five Wapda projects: Mangla refurbishment, the second rehabilitation of Warsak, Harpo hydropower development, rehabilitation of Dargai and capacity enhancement of Chitral. AFD was also reported to be providing a 200,000 euro grant for the Dargai and Chitral projects. This financing package combines new hydropower development and the restoration and upgrading of existing facilities.

Wapda operates several small hydropower stations connected to the national grid, including Rasul, Dargai, Nandipur, Chichoki Malian, Shadiwal, Renala, Jabban, Kurram Garhi, Chitral and Gomal Zam. These power plants have a combined installed capacity of approximately 128MW, although individual capacities and operational conditions vary. Most have been operating for decades. Wear and tear, ageing electromechanical equipment, technological obsolescence and inadequate modernisation have affected their efficiency and availability. Rehabilitation can therefore recover generation currently being lost, without the expense and long gestation period of developing entirely new power infrastructure.

Jabban, also known as Malakand-I, provides an important example of successful rehabilitation. Located on the Swat Canal, the station was commissioned in 1937 with an original capacity of 19.60MW. It ceased operation after a major fire in 2006 and required extensive rehabilitation, including replacing the turbines and associated electromechanical equipment. After AFD-financed rehabilitation in 2013, its installed capacity increased to 22MW. The project shows how an ageing facility can be restored to productive service rather than abandoned.

Rehabilitation and capacity enhancement of Dargai hydropower station is another important undertaking. Commissioned in 1952, the 20MW station is located on the Swat Canal system and uses water discharged from the upstream Jabban station. With AFD support, its installed capacity is being upgraded to 22MW. The same programme covers Chitral hydropower station, a 1MW facility commissioned in 1975, whose capacity is planned to increase to 5MW. The Chitral scheme includes improvements to the intake and power channel, new penstocks and electromechanical equipment, and associated transmission infrastructure. Together, the two projects are intended to add 6MW beyond their original combined capacity.

Pakistan’s hydropower strategy should give rehabilitation and modernisation a more prominent place alongside the construction of new dams and power stations. With realistic project appraisals, timely financing and effective execution, restoring these ageing power plants can deliver additional indigenous renewable electricity

These projects illustrate a basic principle: an existing hydropower station's value does not diminish when its equipment becomes obsolete. Replacing or refurbishing turbines, generators, governors, excitation systems, protection equipment and other components can improve performance and extend the plant’s operating life. Although small stations contribute only a limited share of Wapda’s total generating capacity, these remain valuable because their canals, waterways, civil structures and grid connections are already in place. Rehabilitating these stations can therefore yield additional electricity without the extensive infrastructure development required for a new project.

The next phase of small hydropower rehabilitation includes plans for the Rasul and Renala power stations. In 2023, Wapda invited expressions of interest through newspapers from consultants to review and update feasibility studies, undertake detailed engineering design, and prepare PC-I and tender documents for the rehabilitation, refurbishment and upgrading of both stations. AFD supported the consultancy process.

Rasul hydropower station, located on the Upper Jhelum Canal in Mandi Bahauddin district, was commissioned in 1952. Its two units were originally rated at 11MW each, for a total installed capacity of 22MW. Deterioration of its electromechanical equipment has reduced its effective capacity to approximately 17MW. Rehabilitation is intended to restore the plant’s performance and determine the most appropriate modernisation and capacity-enhancement measures.

Renala hydropower station, located on the Lower Bari Doab Canal in Okara district, was commissioned in March 1925 and is widely recognised as Pakistan’s oldest hydropower station. Its existing installed capacity is approximately 1.10MW. Wapda has examined a scheme to increase its capacity to 4.40MW by making fuller use of the available canal discharge. The upgraded station is projected to generate approximately 25.60 GWh annually, nearly four times its present output. The proposed capacity and generation figures will be firmed up at the feasibility studies and engineering design stage.

Another proposed phase covers rehabilitation and capacity enhancement of the Nandipur, Chichoki Malian, and Shadiwal hydropower stations. These projects, for which Wapda has prepared draft PC-1 proformas during April-December 2025, require detailed technical assessments, substantial investment and firm financing arrangements before implementation. Nandipur, located on the Upper Chenab Canal near Gujranwala, was commissioned in 1963. It has three generating units rated at 4.60MW each, giving it a combined installed capacity of 13.80MW. Wapda’s estimated rehabilitation cost is Rs7.47 billion, including a foreign-exchange component of $23.38 million, according to the draft PC-1.

Chichoki Malian, also situated on the Upper Chenab Canal, near Sheikhupura, has three units with a combined installed capacity of 13.20MW. Commissioned in 1959, the station has experienced a significant decline in generation. Its annual output has fallen to about 25 GWh, down from 47 GWh. The estimated rehabilitation cost is Rs7.41 billion, including a foreign-exchange component of $26.46 million, according to the draft project PC-1.

Shadiwal hydropower station, located on the Upper Jhelum Canal near Gujrat, was commissioned in January 1961. Its licensed installed capacity is 13.50MW, but its effective generating capacity has reportedly fallen to approximately 4MW. Its estimated rehabilitation cost is Rs8.20 billion, including a foreign-exchange component of $29.29 million. These cost figures are project estimates pending approval of feasibility studies and the PC-I document.

For Wapda, securing local financing and the necessary rupee cover will be crucial to implementing these schemes. Concessional foreign loans can ease the financing burden, but do not eliminate the need for domestic funds. Wapda is also committed to the substantial capital requirements of major hydropower projects under construction, making the prioritisation and timely financing of smaller schemes particularly important.

Rehabilitation of ageing small hydropower stations nevertheless deserves greater attention. Unlike greenfield projects, these schemes generally do not require the lengthy development of new dams and powerhouses, large-scale land acquisition or the relocation of communities. Their existing waterways, powerhouses and grid connections provide a substantial infrastructure base. Replacing obsolete equipment and repairing deteriorated structures can restore lost capacity, improve operational efficiency and reliability, and extend the productive life of valuable public assets.

Pakistan’s hydropower strategy should therefore give rehabilitation and modernisation a more prominent place alongside the construction of new dams and power stations. With realistic project appraisals, timely financing and effective execution, restoring these ageing power plants can deliver additional indigenous renewable electricity while making better use of existing infrastructure and other assets. Their individual capacities may be small in the big picture, but their collective contribution to energy security, efficient resource use, and affordable electricity should not be underestimated.


The writer is a retired chairman of the State Engineering Corporation.

More From Money Matters
Cargoes are not a gas plan
By Saqib Ur Rehman Mughal

Cargoes are not a gas plan
By Nayyar Hussain Mirjat

Why intermodal connectivity matters
By Engr Abdul Hanan Aftab

The missing link
By Asif Javed

The real bull market
By Muhammad Farooq